1809-3-001 At the start of a project, a key resource plans to retire. What the project manager should do?
A. Revise the work breakdown structure (WBS).
B.Work with the sponsor to find a suitable replacement for the key resource.
C.Negotiate with the functional manager to obtain to obtain an equal resource.
D.Update the risk register.
1809-3-001 在项目开始时,一名关键资源计划退休。项目经理应该怎么做?
A. 修订工作分解结构(WBS)。
B. 与项目发起人合作,找到适合的替代资源。
C. 与职能经理协商获得一名同等相当资源。
D. 更新风险登记册。
参考答案:D 解析:11.6.3.2 实施风险应对:输出:项目文件更新。一名关键资源计划退休(还未退休)是新识别
的风险,应首先更新风险登记册。
1809-3-002 During a project’s execution phase, the project manager realizes that a stakeholder is consistently
late in responding to sensitive emails. What should the project manager do?
A.Log it in the risk register as a communication issue.
B.Refer to the Control Communications process for an alternative form of communication.
C.Revise the communication channel being used in the communications management plan.
D.Ask the project sponsor to address the issue with the stakeholder.
1809-3-002 在项目执行阶段,项目经理意识到项目相关方一直延迟答复敏感性电子邮件。项目经理应该怎么
做?
A.将其作为一个沟通问题记录在风险登记册中。
B.参阅监督沟通过程,获得替代沟通方式。
C.修订沟通管理计划中使用的沟通渠道。
D.请求项目发起人解决该项目相关方的问题。
参考答案:B 解析:可能影响沟通技术选择的因素包括信息的敏感性和保密性。题目中说到敏感性电子邮件,
说明需要采取相应的安全措施,并在此基础上选择最合适的沟通方式。项目经理意识到相关方一直延迟,首先
要调整沟通方式,如沟通管理计划中没有合适的替代方式再进行修订,之后才是将其记录在风险登记册中。
1809-3-003 When the project starts, the project sponsor notifies the project manager that the cost control must
be given priority. During the planning period, the project manager determines that parts manufactured by
external suppliers are clearly required and unlikely to change. What type of contract should the project manager
use for the supplier?
A.Fixed Price Incentive Fee Contract (FPIF)
B.Cost Plus Incentive Fee Contract(CPIF)
C.Time and Material Contract(T&M)
D.Firm Fixed Price Contract(FFP)
1809-3-003 项目开始时,项目发起人通知项目经理必须优先考虑成本控制。在规划期间,项目经理确定由外部
供应商制造的部件需求明确,不大可能发生变化。项目经理应该对该供应商使用什么合同类型?
A. 总价加激励费用合同(FPIF)
B. 成本加激励费用合同(CPIF)
C. 工料合同(T&M)
D. 固定总价合同(FFP)
参考答案:D 解析:采用总价合同,买方需要准确定义拟采购的产品或服务。虽然可能允许范围变更,但范围
评论