4 、 The project manager invites stakeholders to a project status review. The communication
management plan includes 12 members. There are requests to include for 2 members. How
many additional communication channels are required?
A. 6
B. 27
C. 66
D. 120
项目经理邀请相关方参加项目状态评审。沟通管理计划中包含 12 名成员成员。同时额外请
求增加 2 名相关方。
那么还需要多少个额外沟通渠道?
A.6 个
B.27 个
C.66 个
D.120 个
5、A community interest group has a key interest in a project. They demand that all adjustments
to project cost or schedule be reviewed by them prior to formally issuing the change request.
Where would a project manager document this demand from the community interest group?
A. Requirements documentation
B. Project charter
C. Formal acceptance documentation
D. Change register
社区利益群体在一个项目中具有关键利益。他们要求正式发布变更请求之前,有关项目成本
和进度的所有调整都需要经过他们的评审。项目经理应该将社区利益群体的要求记录在下列
哪种文件当中?
A. 需求文件
B. 项目章程
C. 正式验收文件
D. 变更登记表
6、A project manager has a project team consisting of people in four countries. The project is very
important to the company, and the project manager is concerned about its success. The length of
the project schedule is acceptable. What type of communications method should he use?
A. Informal verbal
B. Formal written
C. Formal verbal
D. Informal written
一项目团队由来自 4 个国家的人组成,该项目很重要,项目经理很担心它能否成功。项目进
度规划得很合理。项目经理应该使用何种沟通方法?
A.非正式口头
B.正式书面
C.正式口头
D.非正式书面