1 Which analysis technique is used to determine the basic underlying reason for a variance,
defect or risk?
A. Root cause analysis
B. Schedule baseline analysis
C. Cost variance analysis
D. Problem analysis
若要确定偏差、缺陷或风险的基本潜在原因,应使用下列哪一项分析技术?
A.根本原因分
B.进度基准分
C.成本偏差分析
D.问题分
2Understanding the Halo effect is very important, because there is such kind of tendency:
AThe interior promotion
BHires the best
CPromotes those who excel at respective area of technology to be project managers
D Promotes those who have had project management training experience to be project
managers
了解光环效应非常重要,因为有这样一种趋势:
A.内部提拔
B.聘用最优秀
C.提拔那些在某技术领域优秀的人作为项目经理
D.提拔那些受过项目管理培训的人作为项目经理
3At what point during the project would the project manager review control measures
AIn the planning stage
BIn the initiation and execution stages
CContinually during the project
DDuring project closure stage
在项目的什么时间点,项目经理将会审查控制措施
A.在计划编制阶段
B.在启动和执行阶段
C.在项目过程中持续审查
D.在项目收尾阶段
4When a project manager approaches the end of their companys big project, the company
s organizational structure, objective and Strategies have changed. What should the project
manager take from the following methods?
A. Speak with the line one manager to ensure the whole resources should continue to complete
the task which assigned before.
B. Check if there is budget available to continue the project following the master schedule.
C. Disregard the change in goals and strategies and continue to run the end.
作业-综合(前三章)
创新 · 专业 · 高效 · 进取 · 共赢
IT 管理·智慧 IT NEEQ838504
2
D. Inquire with the project sponsor as to whether or not the project still fits the company’s
Strategies.
在项目经理快要结束公司的大型项目时,公司的组织结构、目标和战略发生变化项目经理
必须采取下列哪一项措施?
A. 与一线经理谈话保证所有资源能够继续完成之前分派的任务。
B. 检查预算是否足以让项目总进度表执行。
C. 忽视在目标和战略方面发生的变化、继续运行项目,直至项目结束。
D. 询问项目发起人,看项目是否符合公司的战略。
5The main focus of life cycle costing is to :
A. estimate installation costs.
B. estimate the cost of operations and maintenance.
C. consider installation costs when planning the project costs.
D. consider operations and maintenance costs in making project decisions.
生命周期成本法的重点是:
A.估算安装成本。
B.估算营运和维护成本。
C.规划项目成本时,考虑安装成本。
D.作出项目决策时,考虑营运和维护成本。
6During project executing, one of the electrical engineers informs the project manager that the
life cycle cost of the new heating and air conditioning system is higher than the life cycle cost of
another heating and air condition system. What should the project manager do?
A. Determine if there is room in the project budget for the additional cost.
B. Select the product with the lower life cycle cost.
C. Select the product with the best life cycle cost to earned value ratio.
D. Select the product with the lowest maintenance cost to life cycle cost ratio.
项目执行过程中,一电气工程师告诉项目经理某一新空调系统的生命周期成本比另外一空
调系统的生命周期成本要高。项目经理应该怎么做
A. 确定项目是否有足够的费用支付这项额外成本。
B. 选择生命周期成本较低的产品。
C. 选择挣值比率中生命周期成本最佳的产品
D. 选择生命周期成本比率中维修费用最低的产品。
7Which of the following attributes is true for a competency
A. It is a smallest unit of dimension of competence.
B. It affects only a minor part of one’s job.
C. It correlates with performance outside the scope of the job.
D. It can be improved through training and development.
对于资格来说,下列哪一项特征是正确的
A.它是功能最小的单位或维度。
B.它只能影响到一个人工作较小的一部分
C.它与工作范围之外的绩效有关。
D.它可以通过培训和发展得以提高