作业-资源管理
创新 · 专业 · 高效 · 进取 · 共赢
B.强迫
C.撤退
D.合作
6、At a project status team meeting,one team member disagrees with another team member
regarding a corrective action. The debate escalates and they are soon both speeding adamantly.
Other team members are not participating. The project manager directs the team on the
corrective action to use. What conflict resolution technique did the project manager use?
A.Compromising
B.Forcing
C.Withdrawing
D.Smoothing
在一次项目状态团队会议上,一名团队成员与另一名团队成员在纠正措施方面有不同意见.
争论持续升级,很快语气都变得很强硬. 其他团队成员没有参与. 项目经理直接命令团队使
用纠正措施. 项目经理使用的是哪种冲突解决技巧?
A.妥协
B.强迫
C.撤退
D.缓解
7、Retreating from an actual or potential conflict resolution is which of the following techniques
to resolve a conflict?
A. Smoothing/accommodating
B. Withdrawing/avoiding
C. Compromising
D. Collaborating
从实际或潜在冲突解决方案退出属于下列哪一项冲突解决技巧?
A.缓解/包容
B.撤退/回避
C.妥协
D.合作
8、Which of the following conflict resolution techniques is used when the conflicting parties are
uncooperative and unassertive?
A. Withdrawal
B. Confrontation
C. Compromise
D. Smoothing
如果冲突双方虽不配合但也不固执,应该使用下列哪一项冲突管理?
A.回避
B.面对
C.妥协
D.缓解