C.为客户实现交付日期,但并不实施变更。
D.评估实施变更和不实施变更的影响。
4、At a project status meeting with the customer, the customer expects a deliverable that the
project manager does not believe is in scope. The project manager confirms that this deliverable
is a new requirement. What process should the project manager follow?
A.Perform integrated change control
B.Review work breakdown structure
C.Update project management plan
D.Perform risk assessment
在与客户召开的项目状态会议上,客户希望获得某项可交付成果,但是项目经理不认为该可
交付成果属于项目范围。项目经理确认该项目可交付成果是一个新需求。项目经理应该遵循
下列哪一个流程?
A.实施整体变更控制
B.审查工作分解结构
C.更新项目管理计划
D.实施风险评估
5、The project manager has just received a change from the customer that does not affect the
project schedule and is easy to complete. What should the project manager do FIRST?
A. Make the change happen as soon as possible.
B. Contact the project sponsor for permission.
C. Go to the change control board.
D. Evaluate the other components of the triple constraint.
项目经理刚从客户那里收到一项变更,此变更不会影响进度,也很容易完成。项目经理首先
应该做什么?
A.立即实施变更。
B.联系发起人以得到允许。
C.求助变更控制委员会。
D.评估三重约束的其他组成部分。
6、The project was going well when all of a sudden there are were changes to the project coming
from multiple stakeholders. After all the changes were determined, the project manager spent
time with all the stakeholders to find out why there were changes and to discover any more. The
project work has quieted down when a team member casually mentions to the project manager
that the team member added functionality to a product of the project. Do not worry they say, I
did not impact time, cost or quality! What should a project manager do FIRST?
A. Ask the team member how the need for the functionality was determined.
B. Hold a meeting to review the team member's completed work.
C. Look for other added functionality.
D. Ask the team member how he knows there is no time, cost or quality impact.
项目一切进展顺利,突然几个相关方提出一些变更。所有变更确定后,项目经理开始与所有
相关方讨论变更发生的原因,同时发掘是否还存在更多的变更。当一成员突然提到他给产品
增加了一项功能时,全场一片寂静。请不要担心,我不会影响项目的时间、成本及产品质量。