作业-进度管理
创新 · 专业 · 高效 · 进取 · 共赢
IT 管理·智慧 IT NEEQ838504
进度管理
1 A project is seriously delayed. Earned value analysis shows that the project needs to be
completed 10 percent faster than the work has been going. To get the project back on track,
management wants to add 10 people to an activity currently assigned to one person. The project
manager disagrees, noting that such an increase will not produce an increase in speed. This is an
example of:
AThe law of diminishing returns.
BFast tracking.
CEarned value.
DLife cycle costing.
项目已严重滞后。挣值分析的果表明,项目的进度应该比当前 10%。了让项目回
到正规,管理层希望增 10 个人,到原来只有一个工作的活动上来。项目经理并不同意
因为他认为这种安排不一定会导致项目进度的加快。项目经理所说的是:
A. 边际效用递减原理
B.快速跟进
C.挣值
D.生命周期成本
2 Which of the following are GENERALLY illustrated BETTER by bar charts than network
diagrams?
A. Logical relationships
B. Critical paths
C. Resource trade-offs
D. Progress or status
和网络图相比,甘特图能更好的表明:
A.逻辑关系
B.关键路径
C.资源平衡
D.进展及状况
3、在项目的第一阶段后,项目发起人要求项目经理比原始计划提前 21 完成项目,项目
经理分配了额外资源,来满足所计划的开始及完成日期,这称作下面哪一项?
A.资源平衡
B.赶工
C.过度分配
D.快速跟进
4、项目经理因项目时间限制而决定将赶工作为首选措施。应采取下列哪项活动
A.额外增加资源以加快关键路径上的交付
B.压缩重叠活动,努力缩短工期
C.在测试完成前开始产品生
D.采用四倍资源加快非关键路径上的交付
作业-进度管理
创新 · 专业 · 高效 · 进取 · 共赢
IT 管理·智慧 IT NEEQ838504
5What are the two main rules to follow during schedule crashing?
A. Crash the activities on non-critical path and those that cost the least by crashing.
B. Crash the activities on critical path and those that cost the least by crashing.
C. Crash the activities on critical path and those that cost the most by crashing.
D. Crash the activities on non-critical path and those that cost the most by crashing.
赶工期间需要遵循的两个主要原则是什么
A. 对非关键路径上以及赶工成本最少的活动赶工。
B. 对关键路径上以及赶工成本最少的活动赶工。
C. 对关键路径上以及赶工成本最多的活动赶工。
D. 对非关键路径上以及赶工成本最多的活动赶工。
6Which of the following should not be considered when estimating activity durations?
A. Resource capabilities
B. The number of resources assigned to a task
C. Historical data if available
D. Overhead rates
当估算活动持续时间时,不应该考虑下列哪项因素?
A. 资源能力
B. 分配到一项任务的资源数量
C. 历史信息,如果有的话
D. 开销率
7Which at the following techniques is an application of the theory of constraints and is useful
when scheduling constrained resources?
A. Crashing
B. Resource leveling
C. Resource loading
D. Critical chain scheduling
下列哪一项技术属于制约因素理论的应用,并在对制约资源制定进度时起到作用?
A. 赶进度
B. 资源平衡
C. 资源负荷
D. 关键链进度安
8A project manager is trying to coordinate all the activities on the project and has determined
the following:
Activity 1 can start immediately and has an estimated duration of one week. Activity 2 can start
after activity 1 is completed and has an estimated duration of four weeks. Activity 3 can start
after activity 2 is completed and has an estimated duration of five weeks. Activity 4 can start after
activity 1 is completed and has an estimated duration of eight weeks. Both activities 3 and 4 must
be completed before the end of the project. What is the duration of the critical path for this
project?
A.10
B.11