1、A project is nearing completion when the project team learns of new regulations for the
region .where the product is to be installed. The project manager determines that a new feature
will have to be added to ensure compliance, which will impact the resources, schedule, and
budget.
What is needed to communicate and apply the activities required to comply with these new
regulations?
A.Risk breakdown structure (RBS)
B.Change control
C.Issue log
D.Process analysis
项目接近完工,此时项目团队得知即将安装产品的所在地区即将实施新法规。项目经理决
定为确保遵守新法规,必须添加一项新功能,而这将影响到资源、进度计划和预算。为遵守
这些新法规,需要下列哪-项来沟通和应用于需要的活动?
A.风险分解结构(RBS)
B.变更控制
C.问题日志
D.过程分析
2、During project execution, the project team misunderstands how to use a new technology. As a
result, significant rework is required, which increases overall costs.
From what source can the project manager obtain additional funds for the rework?
A.Key stakeholder
B.Management reserve
C.Contingency reserve
D.Project sponsor
在项目执行期间,项目团队对如何使用一项新技术产生误解。结果需要大量返工,导致整
体成本增加。
项目经理可以从什么渠道获得额外的返工资金?
A.关键相关方
B.管理储备
C.应急储备
D.项目发起人
3、During the execution of a project that is at risk of falling behind schedule, the project manager
learns that the company’s most skilled resource will be available from a project that finished
early. The project manager insists that the resource be immediately assigned to their project
team, with the expectation of a positive impact on the project.
What strategy did the project manager apply?
A.Share
B.Accept