C. Project manager should supply an understanding of the risks of the project.
D. Project manager should tell the contract manager how the contracting process should be
handled.
下列哪项最好的说明了项目经理在签订合同时的职责?
A. 项目经理很少参与
B. 项目经理必须是谈判代表
C. 项目经理应表示理解项目的风险
D. 项目经理应告诉合同经理签订合同过程应如何处理
5、During the delivery of a key product, an issue is identified that will delay the project by two
weeks. While assessing the issue, it becomes clear that a team member was aware of this risk a
month earlier but did not escalate it to the project manager. Who is responsible for not
identifying this project risk?
A. Project risk manager
B. Project sponsor
C. Project team member
D. Project manager
在交付一个关键产品期间,识别到一个问题将会延迟项目二周时间. 在评估该问题时,很清
楚的是,某个团队成员一个月前已经注意到这个风险,但是没有向项目经理上报. 谁应该为
没有识别到这个项目风险负责?
A. 项目风险经理
B. 项目发起人
C. 项目团队成员
D. 项目经理
6、Two project managers have just realized that they are in a weak matrix organization and that
their power as project managers is quite limited. One figures out that he is really a project
expediter and the other realizes he is really a project coordinator. How is a project expediter
different from a project coordinator?
A. The project expediter cannot make decisions.
B. The project expediter can make more decisions.
C. The project expediter reports to a higher-level manager.
D. The project expediter has some authority.
两位项目经理认识到他们处于弱矩阵组织中,且权力非常有限。其中一位认为自己其实就是
一名项目联络员,另一位则是一名项目协调员。项目联络员不同于项目协调员之处在于?
A.项目联络员不能做决定。
B.项目联络员可以做很多决定。
C.项目联络员向更高级经理汇报。
D.项目联络员拥有一定权力。
7 、 The project manager determines that there is a lack of understanding of the overall
expectations. What should the project manager do during initiating and planning phases?
A.Obtained approval from the functional managers for resource assignments
B. Establishing and published the project schedule and the work breakdown