1812 第三次模拟考试
1812-3-001. At the start of a project, a key resource plans to retire. What the project manager should do?
A. Revise the work breakdown structure (WBS).
B.Work with the sponsor to find a suitable replacement for the key resource.
C.Negotiate with the functional manager to obtain to obtain an equal resource.
D.Update the risk register.
1812-3-001 在项目开始时,一名关键资源计划退休。项目经理应该怎么做?
A. 修订工作分解结构(WBS)。
B. 与项目发起人合作,找到适合的替代资源。
C. 与职能经理协商获得一名同等相当资源。
D. 更新风险登记册。
1812-3-002. During a project’s execution phase, the project manager realizes that a stakeholder is
consistently late in responding to sensitive emails. What should the project manager do?
A.Log it in the risk register as a communication issue.
B.Refer to the Control Communications process for an alternative form of communication.
C.Revise the communication channel being used in the communications management plan.
D.Ask the project sponsor to address the issue with the stakeholder.
1812-3-002 在项目执行阶段,项目经理意识到项目相关方一直延迟答复敏感性电子邮件。项目经理应该怎
么做?
A.将其作为一个沟通问题记录在风险登记册中。
B.参阅监督沟通过程,获得替代沟通方式。
C.修订沟通管理计划中使用的沟通渠道。
D.请求项目发起人解决该项目相关方的问题。
1812-3-003. When the project starts, the project sponsor notifies the project manager that the cost control
must be given priority. During the planning period, the project manager determines that parts manufactured
by external suppliers are clearly required and unlikely to change. What type of contract should the project
manager use for the supplier?
A.Fixed Price Incentive Fee Contract (FPIF)
B.Cost Plus Incentive Fee Contract(CPIF)
C.Time and Material Contract(T&M)
D.Firm Fixed Price Contract(FFP)
1812-3-003 项目开始时,项目发起人通知项目经理必须优先考虑成本控制。在规划期间,项目经理确定由
外部供应商制造的部件需求明确,不大可能发生变化。项目经理应该对该供应商使用什么合同类型?
A. 总价加激励费用合同(FPIF)
B. 成本加激励费用合同(CPIF)
C. 工料合同(T&M)
D. 固定总价合同(FFP)
1812-3-004. Project progress overruns because of unpredictable project consolidation complexity and
resource availability. To meet the project deadline, the functional manager requires the project manager to
be online without testing. What should the project manager do in advance to avoid this situation?
A.Manage Progress deviations
B.Managing risk
C.Identify risks
D.Identify quality issues