作业-成本管理
创新 · 专业 · 高效 · 进取 · 共赢
成本管理
1、You are asked to prepare a budget for completing a project that was started last year and then
shelved for six months. All the following would be included in the budget EXCEPT?
A. Fixed costs
B. Sunk costs
C. Direct costs
D. Variable costs
公司要你编制一个去年启动、而后搁置的项目的预算。下列哪项不包括在预算中?
A. 固定成本
B. 沉没成本
C. 直接成本
D. 可变成本
2、A project is ahead of schedule, which the budget is overrun. Which of the following could be
the schedule and cost performance indices?
A. schedule performance index is 1.20 and the cost performance index is 1.15
B. schedule performance index is 1.10 and the cost performance index is 0.09
C. schedule performance index is0.95 and the cost performance index is 0.85
D. schedule performance index is 0.90 and the cost performance index is 1.10
某项目进度超前,但是预算超支,下列哪一项可能是项目进度和成本绩效指数?
A. 进度绩效指数为 1.20;成本绩效指数为 1.15
B. 进度绩效指数为 1.10;成本绩效指数为 0.90
C. 进度绩效指数为 0.95;成本绩效指数为 0.85
D. 进度绩效指数为 0.90;成本绩效指数为 1.10
3、During a project performance review meeting, the project manager shares with the team that
actual costs are below the initial estimates and that the schedule is performing well, slightly
better than the planned baseline. Using earned value management, how would CPI and SPI
indexes perform in Situation like this?
A. CPI>1.0; SPI<1.0
B. CPI>1.0; SPI>1.0
C. CPI<1.0; SPI>1.0
D. CPI<1.0; SPI<1.0
在项目绩效审核会上,项目经理告诉团队实际成本低于初始估算,进度执行良好,比计划的
基准还稍好一些。在这种情况下使用挣值管理,CPI 和 SPI 的指数的表现如何?
A. CPI>1.0; SPI<1.0
B. CPI>1.0; SPI>1.0
C. CPI<1.0; SPI>1.0
D. CPI<1.0; SPI<1.0
4、The project stakeholder adds ten more additional activities to the project. What will this
impact the CPI?
A. CPI will become better